Towers

Tower A Tower B

Select Year

Select Month

March 2024

Brigade Komarla Heights Tower A: Lift cladding & corridor tiling works are in progress as on March '24

Brigade Komarla Heights Tower A: Lift cladding & corridor tiling works are in progress

Brigade Komarla Heights Tower A: Basement VDF flooring and painting works are in progress as on March '24

Brigade Komarla Heights Tower A: Basement VDF flooring and painting works are in progress

Brigade Komarla Heights Tower A: Above terrace water proofing works are in progress as on March '24

Brigade Komarla Heights Tower A: Above terrace water proofing works are in progress

Brigade Komarla Heights Tower A: Terrace slab and above terrace structure works completed, Above terrace finishing works, External painting & podium water proofing works are in progress as on March '24

Brigade Komarla Heights Tower A: Terrace slab and above terrace structure works completed, Above terrace finishing works, External painting & podium water proofing works are in progress

February 2024

Brigade Komarla Heights Tower A Structure : Terrace slab completed, Above terrace finishing works & External painting works are in progress as on February '24

Brigade Komarla Heights Tower A Structure : Terrace slab completed, Above terrace finishing works & External painting works are in progress

Brigade Komarla Heights Tower A : Finishing Works as on February '24

Brigade Komarla Heights Tower A : Finishing Works

Brigade Komarla Heights Tower A : Finishing Works as on February '24

Brigade Komarla Heights Tower A : Finishing Works

Brigade Komarla Heights Tower A : Finishing Works as on February '24

Brigade Komarla Heights Tower A : Finishing Works

Brigade Komarla Heights Tower A : Escalator works are in progress as on February '24

Brigade Komarla Heights Tower A : Escalator works are in progress

Brigade Komarla Heights Tower A : Milestone Release On Commencement of Installation of Lifts as on February '24

Brigade Komarla Heights Tower A : Milestone Release On Commencement of Installation of Lifts

Brigade Komarla Heights Tower A : Milestone Release On Commencement of Installation of Lifts as on February '24

Brigade Komarla Heights Tower A : Milestone Release On Commencement of Installation of Lifts

Brigade Komarla Heights Tower A : Milestone Release On Commencement of Installation of Lifts as on February '24

Brigade Komarla Heights Tower A : Milestone Release On Commencement of Installation of Lifts

January 2024

Brigade Komarla Heights Tower A Structure : Terrace Slab Completed, Above Terrace Works & External Painting works are in progress as on January '24

Brigade Komarla Heights Tower A Structure : Terrace Slab Completed, Above Terrace Works & External Painting works are in progress

Brigade Komarla Heights Tower A : Finishing Works as on January '24

Brigade Komarla Heights Tower A : Finishing Works

Brigade Komarla Heights Tower A : Finishing Works as on January '24

Brigade Komarla Heights Tower A : Finishing Works

Brigade Komarla Heights Tower A : Escalator works are in progress as on January '24

Brigade Komarla Heights Tower A : Escalator works are in progress

Brigade Komarla Heights Tower A : Milestone Release On Commencement of Painting 18-25 as on January '24

Brigade Komarla Heights Tower A : Milestone Release On Commencement of Painting 18-25

Brigade Komarla Heights Tower A : Milestone Release On Commencement of Painting 18-25 as on January '24

Brigade Komarla Heights Tower A : Milestone Release On Commencement of Painting 18-25

December 2023

Brigade Komarla Heights Tower A : Finishing Works as on December '23

Brigade Komarla Heights Tower A : Finishing Works

Brigade Komarla Heights Tower A Structure : View From East Side (Terrace Slab Completed, Above Terrace works are in progress) as on December '23

Brigade Komarla Heights Tower A Structure : View From East Side (Terrace Slab Completed, Above Terrace works are in progress)

Brigade Komarla Heights Tower A : Finishing Works as on December '23

Brigade Komarla Heights Tower A : Finishing Works

Brigade Komarla Heights Tower A : Finishing Works as on December '23

Brigade Komarla Heights Tower A : Finishing Works

November 2023

Brigade Komarla Heights Tower A : View From East Side (Terrace slab completed, Above terrace works are in progress) as on November '23

Brigade Komarla Heights Tower A : View From East Side (Terrace slab completed, Above terrace works are in progress)

Brigade Komarla Heights Tower A : Finishing Works as on November '23

Brigade Komarla Heights Tower A : Finishing Works

Brigade Komarla Heights Tower A : Finishing Works as on November '23

Brigade Komarla Heights Tower A : Finishing Works

Brigade Komarla Heights Tower A : Finishing Works as on November '23

Brigade Komarla Heights Tower A : Finishing Works

Brigade Komarla Heights Tower A : Finishing Works as on November '23

Brigade Komarla Heights Tower A : Finishing Works

Brigade Komarla Heights Tower A : Milestone Release On Commencement of Flooring 18th to 25th Floor as on November '23

Brigade Komarla Heights Tower A : Milestone Release On Commencement of Flooring 18th to 25th Floor

Brigade Komarla Heights Tower A : Milestone Release On Commencement of Flooring 18th to 25th Floor as on November '23

Brigade Komarla Heights Tower A : Milestone Release On Commencement of Flooring 18th to 25th Floor

Brigade Komarla Heights Tower A : Milestone Release On Commencement of Painting 9 to 17th Floor as on November '23

Brigade Komarla Heights Tower A : Milestone Release On Commencement of Painting 9 to 17th Floor

Brigade Komarla Heights Tower A : Milestone Release On Commencement of Painting 9 to 17th Floor as on November '23

Brigade Komarla Heights Tower A : Milestone Release On Commencement of Painting 9 to 17th Floor

Brigade Komarla Heights Tower A : Milestone Release On Commencement of Painting 9 to 17th Floor as on November '23

Brigade Komarla Heights Tower A : Milestone Release On Commencement of Painting 9 to 17th Floor

October 2023

Brigade Komarla Heights Tower A : View From East Side (Terrace Slab Completed, Above Terrace works in progress) as on October '23

Brigade Komarla Heights Tower A : View From East Side (Terrace Slab Completed, Above Terrace works in progress)

Brigade Komarla Heights Tower A : Finishing Works. Water proofing 21st floor completed 22nd floor work in progress as on October '23

Brigade Komarla Heights Tower A : Finishing Works. Water proofing 21st floor completed 22nd floor work in progress

Brigade Komarla Heights Tower A : Finishing Works. Tiling works 19th floor completed 20th floor work in progress as on October '23

Brigade Komarla Heights Tower A : Finishing Works. Tiling works 19th floor completed 20th floor work in progress

Brigade Komarla Heights Tower A : Finishing Works. Painting works up to 15th floor work in progress as on October '23

Brigade Komarla Heights Tower A : Finishing Works. Painting works up to 15th floor work in progress

Brigade Komarla Heights Tower A : Finishing Works. UPVC Windows fixing completed till 10th floor as on October '23

Brigade Komarla Heights Tower A : Finishing Works. UPVC Windows fixing completed till 10th floor

September 2023

Brigade Komarla Heights Tower A : View From East Side (Terrace slab completed, Above terrace works in progress) as on September '23

Brigade Komarla Heights Tower A : View From East Side (Terrace slab completed, Above terrace works in progress)

Brigade Komarla Heights Tower A : Water proofing 18th floor completed 19th floor & 20th floor work in progress as on September '23

Brigade Komarla Heights Tower A : Water proofing 18th floor completed 19th floor & 20th floor work in progress

Brigade Komarla Heights Tower A : Tiling works 16th floor completed, 17th floor work in progress as on September '23

Brigade Komarla Heights Tower A : Tiling works 16th floor completed, 17th floor work in progress

Brigade Komarla Heights Tower A : Painting works up to 12th floor work in progress as on September '23

Brigade Komarla Heights Tower A : Painting works up to 12th floor work in progress

Brigade Komarla Heights Tower A : Milestone Release On casting of terrace slab as on September '23

Brigade Komarla Heights Tower A : Milestone Release On casting of terrace slab

August 2023

Brigade Komarla Heights Tower A Structure : View From East Side (23rd floor completed, 24th floor work in progress) as on August '23

Brigade Komarla Heights Tower A Structure : View From East Side (23rd floor completed, 24th floor work in progress)

Brigade Komarla Heights Tower A : Finishing Works and Water proofing 16th floor completed 17th floor work in progress as on August '23

Brigade Komarla Heights Tower A : Finishing Works and Water proofing 16th floor completed 17th floor work in progress

Brigade Komarla Heights Tower A : Finishing Works and Tiling 13th floor completed 14th floor work in progress as on August '23

Brigade Komarla Heights Tower A : Finishing Works and Tiling 13th floor completed 14th floor work in progress

Brigade Komarla Heights Tower A : Finishing Works and Painting works in progress up to 8th floor as on August '23

Brigade Komarla Heights Tower A : Finishing Works and Painting works in progress up to 8th floor

Brigade Komarla Heights Tower A : Milestone Release – On Commencement of flooring from 9th to 17th floor as on August '23

Brigade Komarla Heights Tower A : Milestone Release – On Commencement of flooring from 9th to 17th floor

Brigade Komarla Heights Tower A : Milestone Release – On Commencement of flooring from 9th to 17th floor as on August '23

Brigade Komarla Heights Tower A : Milestone Release – On Commencement of flooring from 9th to 17th floor

Brigade Komarla Heights Tower A : Milestone Release – On Commencement of Painting from GF to 8th floor as on August '23

Brigade Komarla Heights Tower A : Milestone Release – On Commencement of Painting from GF to 8th floor

Brigade Komarla Heights Tower A : Milestone Release – On Commencement of Painting from GF to 8th floor as on August '23

Brigade Komarla Heights Tower A : Milestone Release – On Commencement of Painting from GF to 8th floor

July 2023

Brigade Komarla Heights Tower A Structure : View From East Side (21st Floor Completed, 22nd Floor work in progress) as on July '23

Brigade Komarla Heights Tower A Structure : View From East Side (21st Floor Completed, 22nd Floor work in progress)

Brigade Komarla Heights Tower A : Finishing Works. And Water proofing works in progress up to 13th floor as on July '23

Brigade Komarla Heights Tower A : Finishing Works. And Water proofing works in progress up to 13th floor

Brigade Komarla Heights Tower A : Finishing Works. And Tiling works progress up to 11th floor as on July '23

Brigade Komarla Heights Tower A : Finishing Works. And Tiling works progress up to 11th floor

Brigade Komarla Heights Tower A : Finishing Works. And Painting works in progress up to 8th floor as on July '23

Brigade Komarla Heights Tower A : Finishing Works. And Painting works in progress up to 8th floor

Brigade Komarla Heights Tower A : Milestone Release – On Casting of 20th Floor Slab as on July '23

Brigade Komarla Heights Tower A : Milestone Release – On Casting of 20th Floor Slab

June 2023

Brigade Komarla Heights Tower A : View From East Side (20th floor completed, 21st floor work in progress) as on June '23

Brigade Komarla Heights Tower A : View From East Side (20th floor completed, 21st floor work in progress)

Brigade Komarla Heights Tower A : Finishing Works. Painting works in progress up to 6th floor as on June '23

Brigade Komarla Heights Tower A : Finishing Works. Painting works in progress up to 6th floor

Brigade Komarla Heights Tower A : Finishing Works. Tiling works progress up to 9th floor as on June '23

Brigade Komarla Heights Tower A : Finishing Works. Tiling works progress up to 9th floor

May 2023

Brigade Komarla Heights Tower A : Internal flats floor tiling works are in progress as on May '23

Brigade Komarla Heights Tower A : Internal flats floor tiling works are in progress

Brigade Komarla Heights Tower A : Internal flats painting putty works are in progress as on May '23

Brigade Komarla Heights Tower A : Internal flats painting putty works are in progress

Brigade Komarla Heights Tower A (view from south) : 18th floor slab 100% concreting completed & 19th floor works are in progress as on May '23

Brigade Komarla Heights Tower A (view from south) : 18th floor slab 100% concreting completed & 19th floor works are in progress

Brigade Komarla Heights Tower A (view from North) : 18th floor slab concreting 100% completed & 19th floor works are in progress as on May '23

Brigade Komarla Heights Tower A (view from North) : 18th floor slab concreting 100% completed & 19th floor works are in progress

Brigade Komarla Heights Tower A (view from East side) : 18th floor slab concreting 100% completed & 19th floor works are in progress as on May '23

Brigade Komarla Heights Tower A (view from East side) : 18th floor slab concreting 100% completed & 19th floor works are in progress

Brigade Komarla Heights Tower A : Milestone Release – On Commencement of Flooring GF to 08th Floor as on May '23

Brigade Komarla Heights Tower A : Milestone Release – On Commencement of Flooring GF to 08th Floor

Brigade Komarla Heights Tower A : Milestone Release – On Commencement of Flooring GF to 08th Floor as on May '23

Brigade Komarla Heights Tower A : Milestone Release – On Commencement of Flooring GF to 08th Floor

Brigade Komarla Heights Tower A : Milestone Release – On Commencement of Flooring GF to 08th Floor as on May '23

Brigade Komarla Heights Tower A : Milestone Release – On Commencement of Flooring GF to 08th Floor

Brigade Komarla Heights Tower A : Milestone Release – On Commencement of Flooring GF to 08th Floor as on May '23

Brigade Komarla Heights Tower A : Milestone Release – On Commencement of Flooring GF to 08th Floor

Brigade Komarla Heights Tower A : Milestone Release – On Casting of 16th Floor Slab as on May '23

Brigade Komarla Heights Tower A : Milestone Release – On Casting of 16th Floor Slab

Brigade Komarla Heights Tower A : Milestone Release – On Casting of 16th Floor Slab as on May '23

Brigade Komarla Heights Tower A : Milestone Release – On Casting of 16th Floor Slab

April 2023

Brigade Komarla Heights Tower A (view from south) : 16th floor slab 100% concreting completed & 17th floor works are in progress as on April '23

Brigade Komarla Heights Tower A (view from south) : 16th floor slab 100% concreting completed & 17th floor works are in progress

Brigade Komarla Heights Tower A (view from North) : 16th floor slab concreting 100% completed & 17th floor works are in progress as on April '23

Brigade Komarla Heights Tower A (view from North) : 16th floor slab concreting 100% completed & 17th floor works are in progress

Brigade Komarla Heights Tower A (view from top) : 16th floor slab concreting 100% completed & 17th floor works are in progress as on April '23

Brigade Komarla Heights Tower A (view from top) : 16th floor slab concreting 100% completed & 17th floor works are in progress

Brigade Komarla Heights Tower A (view from east side) : 16th floor slab concreting 100% completed & 17th floor works are in progress as on April '23

Brigade Komarla Heights Tower A (view from east side) : 16th floor slab concreting 100% completed & 17th floor works are in progress

Brigade Komarla Heights Tower A : Internal flats tiling works are in progress as on April '23

Brigade Komarla Heights Tower A : Internal flats tiling works are in progress

Brigade Komarla Heights Tower A : Internal flats painting putty works are in progress as on April '23

Brigade Komarla Heights Tower A : Internal flats painting putty works are in progress

March 2023

Brigade Komarla Heights Tower A (view from south) : 14th floor slab concreting completed & 15th floor works are in progress as on March '23

Brigade Komarla Heights Tower A (view from south) : 14th floor slab concreting completed & 15th floor works are in progress

Brigade Komarla Heights Tower A (view from North) : 14th floor slab concreting completed & 15th floor works are in progress as on March '23

Brigade Komarla Heights Tower A (view from North) : 14th floor slab concreting completed & 15th floor works are in progress

Brigade Komarla Heights Tower A (view from top) : 14th floor slab concreting completed & 15th floor works are in progress as on March '23

Brigade Komarla Heights Tower A (view from top) : 14th floor slab concreting completed & 15th floor works are in progress

Brigade Komarla Heights Tower A (view from East) : 14th floor slab concreting completed & 15th floor works are in progress  as on March '23

Brigade Komarla Heights Tower A (view from East) : 14th floor slab concreting completed & 15th floor works are in progress

Brigade Komarla Heights Tower A : Milestone Release On Casting of 12th Floor slab as on March '23

Brigade Komarla Heights Tower A : Milestone Release On Casting of 12th Floor slab

Brigade Komarla Heights Tower A : Milestone Release On Casting of 12th Floor slab as on March '23

Brigade Komarla Heights Tower A : Milestone Release On Casting of 12th Floor slab

February 2023

Komarla Heights Tower A (view from south) : 11th floor slab concreting completed & 12th floor works are in progress as on February '23

Komarla Heights Tower A (view from south) : 11th floor slab concreting completed & 12th floor works are in progress

Komarla Heights Tower A (view from North) : 12th floor slab concreting completed & 12th floor works are in progress  as on February '23

Komarla Heights Tower A (view from North) : 12th floor slab concreting completed & 12th floor works are in progress

Komarla Heights Tower A (view from East) : 12th floor slab concreting completed & 12th floor works are in progress as on February '23

Komarla Heights Tower A (view from East) : 12th floor slab concreting completed & 12th floor works are in progress

Komarla Heights Tower A (view from North East) : 11th floor slab concreting completed & 12th floor works are in progress as on February '23

Komarla Heights Tower A (view from North East) : 11th floor slab concreting completed & 12th floor works are in progress

January 2023

Komarla Heights Tower A (view from south) : 8th floor concreting completed & 9th floor works are in progress as on January '23

Komarla Heights Tower A (view from south) : 8th floor concreting completed & 9th floor works are in progress

Komarla Heights Tower A (view from North) : 8th floor concreting completed & 9th floor works are in progress as on January '23

Komarla Heights Tower A (view from North) : 8th floor concreting completed & 9th floor works are in progress

Komarla Heights Tower A (view from East) : 8th floor concreting completed & 9th floor works are in progress  as on January '23

Komarla Heights Tower A (view from East) : 8th floor concreting completed & 9th floor works are in progress

Komarla Heights Tower A : Milestone Release - On Casting of 8th Floor Slab as on January '23

Komarla Heights Tower A : Milestone Release - On Casting of 8th Floor Slab

April 2022

Komarla Heights Tower A : Milestone release - On casting of footing/raft as on April '22

Komarla Heights Tower A : Milestone release - On casting of footing/raft

August 2022

Komarla Heights Tower A : Upper Basement 100%  completed. Ground Floor slab works are in progress as on August '22

Komarla Heights Tower A : Upper Basement 100% completed. Ground Floor slab works are in progress

Komarla Heights Tower A : Upper Basement slab concreting completed. Ground floor slab work is in progress as on August '22

Komarla Heights Tower A : (view from top) Upper Basement slab concreting completed. Ground floor slab work is in progress

September 2022

Komarla Heights Tower A (view from East) : First floor slab works are in progress as on September '22

Komarla Heights Tower A (view from East) : First floor slab works are in progress

Komarla Heights Tower A (view from north) : First floor slab works are in progress as on September '22

Komarla Heights Tower A (view from north) : First floor slab works are in progress

Komarla Heights Tower A (view from top) : First floor slab works are in progress as on September '22

Komarla Heights Tower A (view from top) : First floor slab works are in progress

Komarla Heights Tower A : Milestone Release On Casting of Ground Floor Slab as on September '22

Komarla Heights Tower A : Milestone Release On Casting of Ground Floor Slab

October 2022

Komarla Heights Tower A (view from East) : First floor slab concreting completed. Second floor slab aluminium works are in progress as on October '22

Komarla Heights Tower A (view from East) : First floor slab concreting completed. Second floor slab aluminium works are in progress

Komarla Heights Tower A (view from South) : First floor slab concrete completed. Second floor slab aluminium works are in progress as on October '22

Komarla Heights Tower A (view from South) : First floor slab concrete completed. Second floor slab aluminium works are in progress

Komarla Heights Tower A (view from top) : First floor slab concrete completed. Second floor slab aluminium works are in progress as on October '22

Komarla Heights Tower A (view from top) : First floor slab concrete completed. Second floor slab aluminium works are in progress

November 2022

Komarla Heights Tower A : Milestone Release - On Casting of 4th Floor Slab as on November '22

Komarla Heights Tower A : Milestone Release - On Casting of 4th Floor Slab

Tower A (view from East) : Fifth floor slab concreting completed as on November '22

Tower A (view from East) : Fifth floor slab concreting completed

Tower A (view from North) : Fifth floor slab concreting completed  as on November '22

Tower A (view from North) : Fifth floor slab concreting completed

Tower A (view from top) : Fifth floor slab concreting completed  as on November '22

Tower A (view from top) : Fifth floor slab concreting completed

December 2022

Komarla Heights Tower A (view from south) : Seventh floor slab concreting completed & 8th floor slab works are in progress as on December '22

Komarla Heights Tower A (view from south) : Seventh floor slab concreting completed & 8th floor slab works are in progress

Komarla Heights Tower A (view from North) : Seventh floor slab concreting completed & 8th floor slab works are in progress as on December '22

Komarla Heights Tower A (view from North) : Seventh floor slab concreting completed & 8th floor slab works are in progress

Komarla Heights Tower A (view from east) : Seventh floor slab concreting completed  & 8th floor slab works are in progress as on December '22

Komarla Heights Tower A (view from east) : Seventh floor slab concreting completed & 8th floor slab works are in progress